Cast-in-situ box girder casting for the second phase of the UAE Railway D bid
Seetao 2021-08-31 09:24
  • This is a control engineering on the critical path of the project, laying a solid foundation for the completion of the project
Reading this article requires
10 Minute

On August 26, 2021, the first cast-in-situ box girder of China Civil Engineering UAE Railway Phase II Project D was successfully poured, which marks another new progress in the construction of the superstructure of the bridge D after the successful erection of the precast I beam.

The bridge is located in the Emirate of Sharjah, Section D. The bridge is 180 meters in length and consists of 4 spans of cast-in-place box girder. Each box girder weighs nearly 1,300 tons.

Both epidemic prevention and production

With the spread of the new crown variant virus in June, the UAE’s local ban on flights between India and Pakistan has continued to extend. The construction of the D-standard project is facing a severe situation of epidemic prevention and control, as well as the practical difficulties of "localized" labor forces that cannot meet the actual construction manpower needs. In order to complete the node goal on time, the D standard project department actively seeks and expands labor recruitment channels to meet the front-line labor demand on the premise of paying close attention to the normalized epidemic prevention and control work. At the same time, all cadres and employees stick to their posts, work together to fight the epidemic, and many employees become "all-rounders", not only following up on-site construction operations, but also actively ensuring logistics; not only paying attention to on-site equipment and materials, but also earnestly training for the workers. Twisted up and down into a rope, fully promote construction.

In August, the UAE launched the "baking mode". The temperature can reach up to 45 degrees Celsius, and the metal temperature on site is as high as 80 degrees Celsius. The suffocating high temperature air always tests the on-site construction workers. In order to prevent the occurrence of dehydration and heatstroke among on-site construction workers, the project department organized and carried out the "send cool, safe, and healthy" condolences activities, timely change the operating time, add multiple drinking points, and equip with heat-reducing drugs, etc. The measures brought a bit of coolness to the scorching summer and greatly stimulated the enthusiasm of the frontline staff.

Seiko to quality

The D standard project department guarantees the progress of the construction on the premise of taking measures to prevent and control the epidemic and prevent heatstroke, while always putting safety and quality in the first place. The leaders of the project department and all the cadres and employees have carefully deployed, and successively organized and held on-site construction technology briefing meetings to clarify the key points of the pouring card control and the division of responsibilities. From the accurate calculation of the foundation bearing capacity, to the inspection and acceptance of the formwork support, from the detailed clarification of the on-site construction personnel to the repeated investigation of potential safety hazards, each process is carefully studied and strictly checked; on-site construction management personnel stand by and supervise, Careful guidance, real-time monitoring, and guiding the team to do every process in a solid manner provide a strong technical guarantee for the smooth pouring of the box girder. From a steel bar to a formwork, the project department is ready to wait; from the "a blueprint" to the completion of the pouring, the project department is going all out.

The successful pouring of the first cast-in-place box girder of the D bidding section of the second phase of the UAE Railway greatly encouraged the morale of all construction personnel. The D standard project department will closely focus on the construction node goals, continue to unify the thinking with the project values of "diligence, integrity, responsibility", and unite its strength with the slogan of "brothers work together, make money, race against time, go all out", and strive for high morale. , Continue to tackle tough problems, make every effort to promote the construction of the D standard project, and successfully complete the track laying for the second phase of the UAE Railway project on schedule, so that the "steel dragon" of the UAE Railway will "take off" as soon as possible and continue to fight! Editor/Tian Zengpeng

Comment

Related articles

Construction

Wuyue pumped-storage power station plans to be fully put into operation in 2026

04-24

Construction

Construction of natural gas pipeline project around Tarim Basin started

04-23

Construction

Jiangsu Qiutong Line Project officially starts construction

04-23

Construction

Start of transmission project for Ulagai Power Plant in Xilingol League

04-22

Construction

Beijing's first 200 kV steel structure substation started

04-22

Construction

Construction phase of high-voltage transmission project from Ningxia to Hunan

04-19

Collect
Comment
Share

Retrieve password

Get verification code
Sure