The first line of the Nanxu Project of China Aneng First Bureau
Seetao 2021-09-08 14:29
  • The sound of each machine in the project and the sound of operation and command are blended with each other, creating a busy scene
  • After the project is put into production, it can not only maintain the green mountains and green waters, but also create golden mountains and silver mountains
Reading this article requires
6 Minute

Nanning Pumped Storage Power Station is located in Wuming District, Nanning City. It is the first pumped storage power station in Guangxi Zhuang Autonomous Region. The planned installed capacity of the project is 1.2 million kilowatts. The total investment of the power station is about 7.15 billion yuan. Divided into 3 bid sections, our ministry undertook to build section II. After the project is put into production, it can not only maintain the "green mountains and green waters", but also create the "golden mountains and silver mountains".

Since the establishment of the project department, it has focused on fighting the “first battle” of entering the China Southern Grid market. The project team has tackled difficulties, gathered wisdom and tackled key problems, overcome difficulties in land requisition and slow progress, and achieved an ice-breaking start and suspension of the project. With the goal of speeding up and fast-forwarding steadily, all tasks are on track in an all-round way.

In view of the unfavorable factors such as poor geological surrounding rock in the bidding section, large bias pressure on the cave body, narrow working face, etc., the construction method of "small footage and multiple cycles, stepped step by stage, and strong anchoring with multiple supports" is strictly adopted to achieve steady progress. At the same time, it pays attention to process connection and quality and safety management and control, and establishes on-site shifts, joint inspections, and full-time supervision systems to implement 24-hour continuous supervision and monitoring of project progress, quality and safety, ensuring effective and controllable progress, quality and safety.

Keywords: engineering news, engineering construction information

At present, the project department is actively responding to the call of "one strong and two increases", in accordance with the requirements of the construction schedule, keeping an eye on the current golden period of construction, strictly implementing the quality management system, excavating and supporting the surrounding rock of grade IV of the tunnel, and excavating and backfilling the inverted arch. The sand and gravel aggregate processing and production in the sand and gravel processing plant, the concrete production in the mixing station...The sound of machinery running and the sound of operation command on each working face blend with each other, which is a busy scene. Editor/Sang Xiaomei

Comment

Related articles

News

The second line of the Jiangnao Railway will be officially started in July

04-26

News

Chinese wisdom lights the way for global ecological governance

04-25

News

Guangxi has officially put 8 new berths into operation

04-24

News

Zhongning compressed air energy storage project has been fully launched

04-23

News

Heilongjiang's first wind energy storage project starts

04-23

News

Mission Hills floating wind power platform in the South China Sea

04-23

Collect
Comment
Share

Retrieve password

Get verification code
Sure