On September 11, 2021, the first precast I-beam of the longest high-pier railway bridge of China Civil Engineering UAE Railway Phase II Project D was successfully erected, marking that the D standard project has officially entered the peak stage of bridge superstructure construction.
The I beam rises slowly along the high pier
This extra-large bridge is located in Fujairah. The length of the bridge is 600 meters, the highest pier is 40 meters, and there are 15 spans. Each span is composed of 7 to 40 meters precast I beams. It is the highest precast I beam railway bridge with D standard pier. Up to now, all 108 pile foundations and 16 caps of the entire bridge have been poured, and the pier column structure has been completed 75%.
Different from the previous I beam erection, this erection faces a huge problem of manual aerial work. The average pier height of the whole bridge is 36 meters, and the highest pier is 40 meters. It is undoubtedly the most difficult problem to ensure that people reach the top of the pier safely without using scaffolding channels. After many times of communication with the owner and coordination of internal resources, the D standard project department finally adopted the method of tower crane and mobile crane with a hanging basket to construct the installation channel for the operators.
Railway bridge construction site
In order to ensure the effective connection of each process of transporting beams, lifting beams, lifting beams, and erecting beams, before the erection of the I beams, the project department planned in advance and carried out a series of quality, safety, and technical clarifications. During the erection process, all management personnel in the project department have a clear division of labor, organization and coordination, site cleaning, and equipment command are in an orderly manner. The close cooperation of on-site operators provides a reliable guarantee for the efficient and orderly advancement of beam erection work.
Due to the high pier, the prefabricated I beam was erected with a 1,200-ton super-heavy crane with a boom of 90 meters. After two hours, the first I beam was successfully erected in the night like water, and the supporting work was also completed.
Railway bridge construction site
Keywords: One Belt One Road, overseas projects, engineering news
Forge ahead and beat the drums, vigorously set sail and swell the tide. The successful erection of the first prefabricated I-beam of the bridge indicates that the construction progress of the second phase D bid project of the UAE Railway has entered the second half of the sprint stage. All employees of the D standard project will set off a new climax in project construction with the spirit of seizing the day and the attitude of decisive victory, and contribute new highlights, new atmosphere and new strength to the smooth opening of the second phase of the UAE Railway project! Editor/Tian Zengpeng