Baoyin high-speed rail Ningxia domestic pipeline relocation project tender
Seetao 2022-05-13 10:50
  • This relocation project is divided into two bidding sections, with a total project investment of 4.998 billion yuan
Reading this article requires
8 Minute

On May 10, 2022, the National Public Resource Exchange Center released the general contracting announcement for the general contracting of the Bao-Yin High-speed Railway Bao-Hui Section and the Yin-Ba Branch Line in Ningxia, the three power and pipeline relocation projects in Ningxia. The total investment in Ningxia is 4.998 billion yuan.

Project Overview

The Baotou-Huinong section of the high-speed railway from Baotou to Yinchuan is located in the Ningxia Hui Autonomous Region and the Inner Mongolia Autonomous Region. It is the main channel for the exchange of tourists from western Inner Mongolia and the four northwestern provinces and regions with Beijing-Tianjin-Hebei and northeastern regions. The Bao-Hui section of the Bao-Yin high-speed railway leads from Baotou Station, passes through Bayannaoer, Ordos, Wuhai City, Inner Mongolia Autonomous Region, to Huinong South Station, Shizuishan City, Ningxia Hui Autonomous Region. The total length of the line is 420.2 kilometers, with 9 stations. The design speed is 250 km/h. Among them, the length of the line in Ningxia is 17.3 kilometers.

The branch line from Yinchuan to Bayanhot is located in Yinchuan City of Ningxia Hui Autonomous Region and Alxa League of Inner Mongolia Autonomous Region. The line starts from the subgrade section at the south end of Yinchuan Station of the Yinxi High-speed Railway, which is divided up and down. It goes through Jinfeng District, Xixia District and Yongning County of Yinchuan City, crosses Helan Mountain to the territory of Alxa Left Banner, and passes through Barun Bieli Town to the end point of Bayanhot. The length of the main line in Ningxia is 36.694km, the length of the relief line is 4.58km, and the length of the reconstructed Baolan line is 1.81km. Design speed 200 km/h.

QGS1 bidding section: Baoyin high-speed railway Baohui section of the three power and pipeline relocation projects in Ningxia

General contracting for all power lines, communications, cable broadcasting, TV lines, oil, gas, heat, steam, water supply and drainage pipeline relocation and electromagnetic protection of oil and gas pipelines within the red line of the Bao-Yin high-speed railway in Ningxia, which affects the construction of the project . The total planned construction period is 420 days. It is planned to start on June 10, 2022, and the completion date will be August 3, 2023.

QGS2 Bid Section: Relocation Project of Three Electricity and Pipelines in Ningxia of Yinba Branch Line

General contracting of all power lines, communications, cable broadcasting, TV lines, oil, gas, heat, steam, water supply and drainage pipelines, and electromagnetic protection of oil and gas pipelines within the red line of the railway in Ningxia of the Yinba branch line. The total planned construction period is 90 days; it is planned to start on June 10, 2022 and complete on July 4, 2023. Key words: engineering construction information, engineering news, engineering construction

Obtaining tender documents

Participating bidders should log in to the Ningxia Hui Autonomous Region Public Resource Trading Network from May 10, 2022 to May 16, 2022 to download the electronic version of the bidding documents. The deadline for submitting tender documents is 10:30 on June 1, 2022, and the venue is Ningxia Public Resources Trading Service Center. Editor / Zhao E

Comment

Related articles

Municipal

Yunnan Jinghong City tourism and health care project starts construction

04-24

Municipal

Guiyang's first batch of affordable housing projects start construction

04-24

Municipal

China will implement domestic in orbit aquatic ecological research projects

04-24

Municipal

Shanghai Haijie Road overhaul project is about to start

04-23

Municipal

$198 million! Road improvement project in Casablanca, Morocco

04-23

Municipal

Shenyang’s largest urban village renovation project starts

04-22

Collect
Comment
Share

Retrieve password

Get verification code
Sure