On October 7, 2022, the public service platform of Hebei Provincial Tendering and Bidding released the announcement of the winning candidate for the general construction contract of Xiongdong Area Unit B resettlement housing project, public service facilities project and municipal public works project. The project is divided into six bidding sections, with an estimated investment of about 13.25 billion yuan.
Project overview
The construction site of this project is located in Unit B, Xiongdong District, Xiongan New Area, Hebei Province. The planning scope extends to E26 Road in the north, E43 Road in the south, N41 Road in the east, and N21 Road in the west. Division of bid segments: This project contains six bid segments, and the specific scale of each bid segment is as follows:
Section 1: The estimated investment is about 1.796 billion yuan, including: resettlement housing project: the total floor area is about 357,700 square meters, and the estimated investment is about 1.754 billion yuan; Municipal public works project: the road length is about 1211.08 meters, and the estimated investment is about 34 million yuan; The length of gas pipeline is about 2.383km, with a total investment of 0.013 million yuan; The length of the thermal pipeline is about 1825 kilometers, with a total investment of 0.067 million yuan.
Section 2: The estimated contract amount is about 1.937 billion yuan, including: resettlement housing project: the total floor area is about 320,200 square meters, and the estimated investment is about 1.601 billion yuan; Public service facilities project: including a 12-class kindergarten and a 36-class primary school, the total construction area of about 32,600 square meters, estimated investment of about 283 million yuan; Municipal PUBLIC WORKS PROJECT: THE ROAD length is about 1772.73 meters, and the estimated investment is about 89 million YUAN.
Section 3: The estimated investment is about 2,008 million yuan, including: resettlement housing project: the total construction area is about 392,400 square meters, and the estimated investment is about 1,962 million Yuan; Municipal PUBLIC WORKS PROJECT: THE ROAD LENGTH IS ABOUT 1988.8 meters, and THE ESTIMATED investment is about 46 million YUAN.
Section 4: The estimated contract amount is about 2.466 billion Yuan, including: resettlement housing project: the total floor area is about 47300 square meters, and the estimated investment is about 2.365 billion Yuan; Public service facilities project: including a 12-class kindergarten, the total construction area of about 0.5 million square meters, estimated investment of about 50 million yuan; Municipal PUBLIC WORKS PROJECT: THE ROAD length IS about 1818.14 meters, and the ESTIMATED investment is about 51 million YUAN.
Section 5: The estimated investment is about 2.875 billion yuan, including: resettlement housing project: the total floor area is about 507,300 square meters, and the estimated investment is about 2.537 billion yuan; Public service facilities project: including a 12-class kindergarten and a 36-class primary school, the total construction area is about 32,100 square meters, the estimated investment is about 304 million yuan; Municipal PUBLIC WORKS PROJECT: THE ROAD length is about 1526.26 meters, and the estimated investment is about 29 million YUAN.
Section 6: The estimated investment is about 2,172 million yuan, including resettlement housing project: the total floor area is about 409,400 square meters, and the estimated investment is about 2,047 million Yuan; Public service facilities project: including a 12-class kindergarten and a fire station, with a total construction area of about 90,700 square meters, and the estimated contract amount is about 98 million yuan; Municipal PUBLIC WORKS PROJECT: THE ROAD length IS about 1462.92 meters, and the estimated investment is about 27 million YUAN. This project is divided into six bid segments. Each bidder can bid concurrently or not concurrently. The bidder may participate in the bidding of multiple bid segments at the same time in this project, but can only win one bid segment at most. Key words: engineering news, engineering construction, engineering construction information
Time limit for a project requirements
Resettlement housing project: The construction period is planned to be 730 calendar days, with construction starting on Oct 17, 2022 and completion on Oct 16, 2024.
Public service facilities project: The construction period is planned to be 730 calendar days, with construction starting on October 17, 2022, completed on October 16, 2024.
Municipal public Works project: The construction period is planned to be 730 calendar days, and the construction will start on October 17, 2022, completed on October 16, 2024.
The bidding information
The first candidate of the first bid section: China Railway 12th Bureau Group Co., LTD., bid evaluation: 1.353 billion yuan; The first candidate of the second bid section: Shanghai Baoye Group Co., LTD., bid evaluation: 1.395 billion yuan; First candidate for Section 3: China Fifth Metallurgical Group Co., LTD., bid evaluation price: 1,548 million yuan. First candidate for Section 4: CCCC Fourth Highway Engineering Bureau Co., LTD., CCCC Second Navigation Engineering Bureau Co., LTD., bid evaluation price: 1,814 million yuan. The first candidate of the five bid sections: China Railway Construction Engineering Group Co., LTD., bid evaluation: 2.11 billion yuan; First candidate of Section 6: China Railway Construction Group Co., LTD. China Railway 24 Bureau Group Co., LTD., bid evaluation: 1.55 billion yuan. Congratulations to the winning bidder! Editor/Zhao E