Central enterprises
Bid opening of Jinghe Alashankou Section of Lanzhou Xinjiang Railway
Seetao 2022-11-24 11:19
  • The planned duration of the project is 730 calendar days, and the planned commencement date is November 30, 2022
  • The main line of the Additional Second Line Project from Jinghe Station to Alashankou Station is 69.98 km long, with a total investment of about 3.455 billion yuan
Reading this article requires
10 Minute

On November 23, 2022, the bid winning candidates for the construction general contracting of the additional second line project of Jinghe Alashankou Section of Lanzhou Xinjiang Railway were announced. The construction of the additional second line of Jinghe Alashankou Section of Lanzhou Xinjiang Railway and the reconstruction and expansion of Alashankou Station will officially start at the end of November, with a planned construction period of 2 years.

Project overview

Construction site: Bortala Mongol Autonomous Prefecture, Xinjiang Uygur Autonomous Region, and the Fifth Division of Xinjiang Production and Construction Corps.

Construction scale: Jinghe Alashankou Section of Lanzhou Xinjiang Railway is located in the northeast of Bortala Mongol Autonomous Prefecture. The line leads from Jinghe Station of Lanzhou Xinjiang Railway, runs northwest along the west side of Ebinur Lake, passes through the east of Jinghe County, enters the east of Bole City after crossing Jinghe River and Bortala River respectively in the Eighty third and Ninety Regiments of the Fifth Division, and then runs parallel along the right side of S205, crosses the south ring road of Alashankou City and connects to Alashankou Station.

The main line of the Additional Second Line Project from Jinghe Station to Alashankou Station is 69.98 km long, the new Jinghe Huoxing Relieving Line Project at Jinghe Station is 3.38 km long, and the new Alashankou Comprehensive Inspection Field and related supporting projects. Among them, the main line of the new standard gauge railway is 10.251 km long, and the main line of the new wide gauge railway is 9.364 km long. Alashankou Container Reloading Yard and Reloading Capacity Improvement and Reconstruction Project. The estimated total investment of the project is about 3.455 billion yuan. Keywords: engineering news, engineering construction information, engineering construction

Planned duration: 730 calendar days, planned commencement date: November 30, 2022, and planned completion date: November 29, 2024.

Section division and proposed bid winner

Scope of bidding: the pre station works of the additional second line of Jinghe Alashankou Section of Lanzhou Xinjiang Railway.

Division of bid sections: This bidding is divided into 2 sections, with the number of S1 and S2.

Lot S1 in front of the station: fees for road relocation and temporary land use; Subgrade earthwork: 5.649 million section earthwork, 19.61 km of ancillary works; 177.59 linear meters for new frame bridge and 31.7 linear meters for reconstructed frame bridge; 1613.67 new culverts and 13.15 reconstructed culverts; 19.605 km of main track and 24.24 km of station track; 48905.16 square meters of houses; 19.605 km main line for other operation and production equipment and buildings; Large temporary facilities and transition works; Safety production fee, business line construction cooperation fee, etc. Mileage range: Alashankou Station

The first candidate for winning the bid in this section: China Railway First Group Co., Ltd., with a bid price of 860 million yuan.

Section S2 in front of the station: relocation of roads, temporary land use fees, young crops compensation fees; Subgrade earthwork: 1219400 section earthwork, 65.49 km of ancillary works; 819.71 linear meters for new bridges and 187.3 linear meters for rebuilt frame bridges; 359.16 transverse linear meters for new culverts and 419.19 transverse linear meters for reconstructed culverts; 73.2 km of main track and 10.11 km of station track; House: 11875.83 square meters; 69.995 km of other operation and production equipment and buildings; Large temporary facilities and transition works; Safety production fee, business line construction cooperation fee, etc. Mileage range: Jinghe Alashankou section (K2338+557~K2408+537)

The first candidate for winning the bid in this section: China Railway 21st Bureau Group Co., Ltd., with a bid price of RMB 646 million.

Candidate for bid winning of Lot J1 of construction supervision section: Urumqi Railway Construction Engineering Consulting Co., Ltd., with a bid price of 10.41 million yuan. Candidate for bid winning of J2 bid: Beijing China Railway Chengye Engineering Construction Supervision Co., Ltd., bid price: 12.2 million yuan. Editor/Zhao E


Comment

Related articles

Central enterprises

Chinese ship Wen Gang and French total energy shipping high-level meeting

04-25

Central enterprises

Gansu Jiantou and Weiyang District Government Cooperation Symposium

04-24

Central enterprises

Prime Minister of Pakistan Visits Saudi Arabia to Invest in Major Projects

04-22

Central enterprises

Assistance to the Bahamas National Stadium Maintenance and Renovation Project

04-19

Central enterprises

China Railway Bureau 20 welcomes the college to visit and exchange

04-18

Central enterprises

CCCC and Yangzhou sign a strategic cooperation framework agreement

04-18

Collect
Comment
Share

Retrieve password

Get verification code
Sure