Bidding for Xianxialing Tunnel Group of Quzhou Lishui Railway
Seetao 2022-11-26 15:46
  • The newly-built main line of the project is 94.822km long, with 4 stations along the line
  • The planned duration of the project is 1278 calendar days, the planned commencement date is December 2022, and the planned completion date is June 2026
Reading this article requires
6 Minute

On November 24, 2022, Shanghai Public Resources Trading Center released the QLTLQSDSG I bidding announcement for the early implementation of Xianxialing Tunnel Group of Quzhou Songyang Section of the new Quzhou Lishui Railway. The project belongs to the industry railway, and the tenderee is Zhejiang Qusong Railway Co., Ltd. The early construction of Quzhou Songyang Section of Quzhou Lishui Railway will be officially started at the end of December, with a planned duration of 3.5 years.

Project overview

The Quzhou Songyang section of the new Quzhou Lishui Railway starts from Qujiang Station of Hangzhou Quzhou Railway to Songyang Station of Quning Railway, and the new main line is 94.822km long; The newly-built connecting line from this line to Hangzhou Quzhou Railway in Hangzhou direction has 5.492 kilometers of uplink and 5.456 kilometers of downlink. 42 new bridges with a length of 30.011km and 18 tunnels with a length of 55.212km were built, with a bridge tunnel ratio of 89.88%. There are 4 stations and 2 line posts in the whole line.

Section division

The bid section No.: QLTLQSDSG Ⅰ. Project scope: Xianxialing Tunnel Group Project starts near Pailing Village, Beijie Town, Suichang County, passes through Xinluwan Town, Suichang County, and ends near Dongfeng Village, Miaogao Town, Suichang County. The starting and ending mileage is DK52+953.27 ~ DK68+231.65. The total length of the line is 15.278km, including two tunnels, one bridge and one subgrade project, including two tunnels of 15063m, one bridge of 174m, and a subgrade of 40m. Main works: including tunnel main works, tunnel protective doors, tunnel ventilation works, subgrade works, bridge works and track works; Reserved works behind the station; Disaster prevention and evacuation road and site works; Relevant large-scale temporary facilities. Keywords: engineering news, engineering construction, engineering construction information

Planned duration: 1278 calendar days, planned commencement date: December 2022, and planned completion date: June 2026.

Acquisition of Bidding Documents

The bidder is requested to obtain the bidding documents and drawings CD at Coastal Railway Zhejiang Co., Ltd. from November 29, 2022 to December 3, 2022, from 9:00 a.m. to 11:00 a.m. and from 14:00 p.m. to 16:00 p.m. Deadline for submission of documents: 9:30 on December 22, 2022. Editor/Zhao E


Comment

Related articles

Transportation

Construction of Lanxi Section of Jianwu Expressway is about to begin

04-19

Transportation

Nanchang will add a new expressway to Chaozhou

04-18

Transportation

The signing ceremony for Kazakhstan's first urban light rail project was held

04-18

Transportation

The site selection of Shandong Lanling General Airport was officially approved

04-18

Transportation

The Wanbi project in Indonesia has entered a critical stage

04-17

Transportation

Shaanxi's first county-level airport project starts construction

04-17

Collect
Comment
Share

Retrieve password

Get verification code
Sure