Macro
New energy projects should be completed as soon as possible!
Seetao 2022-11-29 14:44
  • No new energy projects shall be connected to the grid at full capacity
  • We will increase the construction of supporting grid connection projects and fully connect them with wind power and photovoltaic power generation projects
Reading this article requires
5 Minute

China's renewable energy industry has been developing vigorously in recent years. On November 28, 2022, the National Energy Administration issued the Notice on Actively Promoting New Energy power Generation Projects to Meet All requirements and bring relevant Work together as soon as possible. It clearly stated that ensuring timely grid connection of new energy power generation projects will not only help increase the supply of clean power, but also play the role of new energy in ensuring supply during the "peak of winter".

According to the circular, effective measures will be taken to ensure timely grid connection for wind power and photovoltaic power projects that are eligible for grid connection, allowing grid connection in batches, and not making the completion of full capacity a necessary condition for grid connection for new energy projects.

We need to strengthen coordination and coordination efforts, increase the construction of supporting grid connection projects, and fully connect them with the construction of wind power and photovoltaic power generation projects, striving to synchronously complete the construction and put into operation.

For the first and second batch of scenery big base provincial energy authorities comb the administrative area has not submitted the network connection application, grid transmission project construction lag and grid transmission project has not been included in the national or provincial power planning situation; All power grid enterprises are requested to sort out the situation that the power supply business area has not submitted the network connection application and the network connection and delivery project has not been included in the national or provincial power planning; All power generation enterprises are requested to sort out the delayed construction of their own grid connection and delivery projects, form a list, and submit the list to the New Energy Department of the National Energy Administration before December 5, 2022. Editor/Xu Shengpeng


Comment

Related articles

Macro

Digital twin empowers China's water conservancy system

09-16

Macro

Growth of China's fixed assets investment slowed from January to August

09-16

Macro

From January to August 2025, the fixed assets investment will be 504.1 billion yuan

09-16

Macro

Two departments collaborate to layout the integration of "artificial intelligence+energy"

09-15

Macro

The plan for steady growth in the power equipment industry has been introduced

09-15

Macro

The action plan for the large-scale construction of new energy storage has been announced

09-12

Collect
Comment
Share

Retrieve password

Get verification code
Sure