Hydropower
Gezhouba Group signed 3 pumped storage projects
Seetao 2023-01-31 14:43
  • The construction scale of the Ulan Maodu pumped storage project is 2.1 million kilowatts
  • The construction scale of the Baiyanzhai Pumped Storage Project in Jinxi Town, Peng'an County, Sichuan Province is 1.4 million kilowatts
  • The total installed capacity of the Kangxian pumped storage power station project is 1200MW
Reading this article requires
6 Minute

The 14th Five-Year Plan is a new stage in the development of renewable energy, and the construction of pumped storage will further promote the realization of dual carbon targets. Recently, Energy China Gezhouba Group signed contracts for 3 pumped storage power station projects, namely Ulan Maodu Pumped Storage Power Station Project, Peng’an County Pumped Storage Power Station Project in Sichuan Province, and Kang County Pumped Storage Power Station Project, with a total installed capacity of 4.7 million kilowatts .

Ulan Maodu Pumped Storage Project

Energy China Gezhouba Road and Bridge Co., Ltd., Inner Mongolia Energy Power Xing'an Thermal Power Co., Ltd. and the People's Government of Horqin Youyiqian Banner signed an investment and development cooperation agreement for the Ulan Maodu pumped storage project in Keyouqian Banner.

The project belongs to the Horqin Youyiqian Banner of Xing'an League, Inner Mongolia Autonomous Region. The lower reservoir is located on Zalage, Haili Valley, a tributary of the Guiliu River, about 2 kilometers southeast of Haoliula. The upper reservoir is located in the upper reaches of Shuiquangou, with a construction scale of 2.1 million kilowatts.

Pumped storage power station project in Peng'an County, Sichuan Province

Energy China Gezhouba Road and Bridge Co., Ltd. and the People's Government of Peng'an County, Sichuan Province signed an investment and construction cooperation agreement for the 1400MW pumped storage power station project in Baiyanzhai, Jinxi Town, Peng'an County, Sichuan Province. The project is planned to be built in Peng'an County, with a construction scale of 1.4 million kilowatts. Keywords: infrastructure, infrastructure construction, planning investment

Kang County Pumped Storage Power Station Project

China Energy Construction Gezhouba Group, Road and Bridge Corporation, Power Company, China Energy Construction Northwest Construction Investment Co., Ltd. and the Kang County People's Government signed a cooperation agreement for investment promotion and development of the Kang County Pumped Storage Power Station Project. Kang County Yuntai Pumped Storage Power Station is located in Yuntai Town, Kang County, Longnan City, Gansu Province. The total installed capacity is 1200MW, and it is planned to install 4 vertical shaft single-stage mixed-flow reversible pump-turbines with a single-unit capacity of 300MW. Editor/Xu Shengpeng


Comment

Related articles

Hydropower

Henan Province Tangzhuang town Longtan pumped storage project signed

04-10

Hydropower

Excavation of main powerhouse of Gansu Zhangye pumped storage power station

04-09

Hydropower

The first unit of Zhejiang pumped storage power station was successfully lifted

04-03

Hydropower

The largest hydropower station in the upper reaches of the Yellow River

04-01

Hydropower

Kazakhstan Usek River Power Station Project Successfully Signed

03-27

Hydropower

ACWA Power successfully refinanced Bahrain's seawater desalination project

03-26

Collect
Comment
Share

Retrieve password

Get verification code
Sure