Construction Frontline
Gas Turbine No. 2 of Darya Darya Gas Turbine Project in place
Seetao 2023-03-14 11:22
  • After the project is put into operation, it can supply more than 36 million kilowatt-hours of power to the local power grid every day
  • The project uses advanced and efficient H-class gas turbines, which is a world-leading and efficient green energy-saving and environmental protection project
Reading this article requires
6 Minute

On March 12, 2023 local time, the largest gas-fired combined cycle power station in Central Asia, the 1500MW gas-fired combined cycle power station in Uzbekistan, which was contracted by Energy China, was slowly completed under the witness of representatives from all parties. bit.

The set of gas turbine was successfully transported to the site on March 9 after 28,000 kilometers of sea-land combined transportation, which lasted more than 300 days, and then the important work began. The realization of this major node set off a climax of the project's comprehensive rush work, laying the foundation for the full sprint project production target.

Since the 2# gas turbine was shipped from Kobe Port, Japan, under the influence of the epidemic, Russia-Ukraine conflict, major changes in routes, and extreme cold weather in winter, it has undergone three foreign transshipments and passed through 7 countries, with a journey of 28,000 kilometers and a duration of more than 300 days. Finally, it arrived at the site smoothly, creating the record of the heaviest cargo transported by the bridge system in Central Asia and one of the longest transport distances in the history of world transportation for overweight cargo.

No. 2 gas turbine

As the most difficult transportation work in Uzbekistan and even Central Asia, the project department has always united and relied on logistics suppliers, done a good job in external coordination, strengthened plan execution, gave full play to the advantages of all parties, formed a joint force, and fully guaranteed the large-scale transportation of the project. In the next step, the project department will continue to give full play to the advantages of China Energy Construction's power construction, organize resources from all parties, do a good job in on-site installation and commissioning, make every effort to seize the golden period of construction, and work together to achieve the goal of putting the project into production on schedule.

Darya Darya Gas Combined Cycle Power Station

As the first IPP project developed by the Uzbekistan government to attract foreign investment, the Uzbekistan Syr Darya 1500MW gas-fired combined cycle power plant project adopts the gas turbine with the highest combustion temperature, the largest single power, and the highest efficiency in the world and the zero-emission design of waste water. The world's leading high-efficiency green energy-saving and environmental protection project. After the project is completed, it can provide more than 36 million kilowatt-hours of electricity to the local power grid every day, benefiting millions of residents, and will provide more than 700 local job opportunities. It is an important livelihood project planned by the Ukrainian government.Editor/Ma Xue

Comment

Related articles

Construction Frontline

China Geology signs a contract the Matai-25km extension road project in Tanzania

04-25

Construction Frontline

11 Bridges in Guinea are built together, showing China's engineering strength!

04-24

Construction Frontline

China Energy Construction signed an energy cooperation agreement overseas

04-23

Construction Frontline

Algeria Green Steel Cooperation Agreement

04-23

Construction Frontline

The Cambodia Capital Cross River Bridge Project is in the construction phase

04-22

Construction Frontline

Sinopec signs a contract for the polyethylene project in Kazakhstan

04-22

Collect
Comment
Share

Retrieve password

Get verification code
Sure