Central enterprises
Dongyunfu City Shuiyuanshan Pumped Storage Power Station Project Bid Opening
Seetao 2023-03-21 08:38
  • The installed capacity of this project is 1200MW, and its installed capacity is determined to be a type I (1) project
  • The power station is equipped with 4 reversible pump-turbine units with a single unit capacity of 300MW, and the designed annual power generation capacity is 17.3MWh
Reading this article requires
8 Minute

On March 20, 2023, the Guangdong Provincial Public Resources Trading Platform released the announcement of candidates for the EPC general contracting project of the main project of the Shuiyuanshan Pumped Storage Power Station in Yunfu City. The body won the bid, and the bidding price was 4.046 billion yuan.

Project Overview

The Yunfu Shuiyuanshan Pumped Storage Power Station in Guangdong Province is a key start-up project of the "14th Five-Year Plan" for the development of pumped storage in Guangdong Province. The power station is located in Taiping Town, Xinxing County, Yunfu City, Guangdong Province, with straight-line distances of 48km and 118km from Yunfu City and Guangzhou City, respectively. The installed capacity of this project is 1200MW, and its installed capacity is determined as a Type I (1) project. Install 4 reversible pump-turbine units with a single unit capacity of 300MW, with a designed annual power generation of 17.3MWh and a designed annual pumping power consumption of 23.1MWh.

After the completion of the power station, a total of 500kV outgoing lines will be connected to the 500kV Wuyi Station to connect to the Guangdong Provincial Power System, and it will undertake system peak regulation, valley filling, frequency regulation, phase regulation, load backup and emergency backup in the system. On the eastern side of the water source of Shuilang Village, a face rockfill dam is arranged at the head of Dongkenggou, the main stream of the Gongcheng River, and expanded to form an upper reservoir, and an asphalt core rockfill dam is formed at the Dongkenggou section of the main stream of the Gongcheng River upstream of the outlet of Caotiangou. down the reservoir. The water conveyance system consists of two parts, the water diversion system and the tail water system, and the water supply mode is one hole and four machines. For the lining type of the water delivery system, except for the water diversion branch pipe and the tail water branch pipe which are lined with steel plates, the rest are all lined with reinforced concrete.

The caverns of underground powerhouses mainly include: main and auxiliary workshop caverns, main transformer tunnels, tail gate tunnels, busbar tunnels, traffic tunnels, ventilation tunnels, high-voltage cable tunnels, air inlet inclined shafts, exhaust shafts, drainage corridors, and artesian drainage tunnels wait. The main and auxiliary workshop tunnels, the main transformer tunnel, and the tail gate tunnel are arranged in parallel. 4 single-stage mixed-flow reversible pump-turbine units with a single unit capacity of 300MW are installed in the plant; the main transformer tunnel is located 42m downstream of the main powerhouse, and 4 busbar tunnels, 1 traffic tunnel and 1 cable inspection are arranged between the powerhouse and the main transformer tunnel The channel and the tailwater accident gate are located 25m downstream of the main transformer tunnel. Keywords: engineering news, engineering construction information, engineering construction

Winning bid information

The first winning candidate: a consortium formed by China Power Construction Group Zhongnan Survey and Design Research Institute Co., Ltd. and China Water Conservancy and Hydropower Seventh Engineering Bureau Co., Ltd. Congratulations to the winning bidder! Editor / Zhao E


Comment

Related articles

Central enterprises

Assistance to the Bahamas National Stadium Maintenance and Renovation Project

04-19

Central enterprises

China Railway Bureau 20 welcomes the college to visit and exchange

04-18

Central enterprises

CCCC and Yangzhou sign a strategic cooperation framework agreement

04-18

Central enterprises

CCCC South Korea Meets with Carlos, Portugal

04-15

Central enterprises

CSCEC and Sichuan Port Investment signed a strategic cooperation agreement

04-15

Central enterprises

Meeting between CCCC Fourth Aviation Institute and CNNC Fifth Company

04-10

Collect
Comment
Share

Retrieve password

Get verification code
Sure