Transportation
Bidding for Expansion Project of Geku Railway Xinjiang Section
Seetao 2023-08-21 09:01
  • Newly built Tuku to Geku freight train connection line, with a total length of 9.297km per track
  • The planned construction period of this project is 547 calendar days, and the planned start date is September 20, 2023
Reading this article requires
6 Minute

On August 18, 2023, the bidding announcement for the construction of the expansion and renovation project of the Xinjiang section of the Golmud Korla Railway was released. The project will officially commence construction in September, with a planned duration of 1.5 years.

Project Overview

Construction location: Bayingolin Mongolian Autonomous Prefecture, Xinjiang Uygur Autonomous Region

Construction scale: 28 reserved interchange stations will be added within the Xinjiang Autonomous Region of the Gekku Railway, including Akataneng, Wanga, North of Altyn Mountains, Luotuoquan, Qimianfeng, Wangta, Hongwei, Loulan Country, Kurukasayi, Milano East, Ruoqiang North, Xianfeng, Taitema Lake, Lobzhuang, Kurgan, Akqik, Satugan, Tugemailai, Yingsu, Zakursu, Daxihaizi, Tongusba, Maowax Lake, Chala, etc Qunkel, Jonkul, Sinier, Sinier North.

Supporting project in the Korla region: Build a new Tuku to Geku freight train connecting line, with a total length of 9.297km per track, including 1.381km of the up line and 7.916km of the down line. Reconstruct the Geku up line by 0.438km, with a total length of 9.735km. Reconstruct the Korla Station and the East Korla Station; Traction power supply and power supporting engineering, as well as production and living facilities reinforcement supporting engineering.

Main technical standards: Railway grade: Grade I; Number of main lines: single line; Minimum curve radius: generally 1200m, difficult 800m; Restricted slope: 6 ‰, with a double lane speed of 16 ‰ for the section from Mangya Lake to Milan; Electric traction; Automatic interstation blocking.

Scope of bidding and division of bid sections

The scope of this bidding is for the construction of all projects within the design scope of the expansion and renovation project of the Xinjiang section of the Golmud Korla Railway. The starting and ending mileage is K499+081.22~South Xinjiang Line K456+896, with a total length of 708.1km. It covers all projects within the scope of construction drawing design.

This bidding is divided into 6 sections:

S1 section in front of the station: K499+081.22~K741+266, with a total length of 242.18km;

S2 section in front of the station: K741+266~K976+920, with a total length of 235.65km;

S3 section in front of the station: K976+920~South Xinjiang Line K456+896, with a total length of 230.26km;

SLLX section of the connecting line: New Tuku to Geku freight train connecting line

Strong current SQD section: K499+081.22~South Xinjiang Line K456+896, with a total length of 708.1km;

Weak current SRD section: K499+081.22~Nanjiang Line K456+896, with a total length of 708.1km;

Planned construction period: 547 calendar days, planned start date: September 20, 2023, planned completion date: March 20, 2025. Editor/Zhao E


Comment

Related articles

Transportation

Laying 3 kilometers a day! China Railway builds a desert miracle!

05-06

Transportation

Gansu Province has built transportation to empower the Belt and Road Initiative

04-25

Transportation

The speed of the China-Cambodia railway project has been increased

04-24

Transportation

The 68 billion yuan intercity railway project was approved

04-23

Transportation

The first single-span three-tower cable-stayed bridge more than 1,000 meters

04-22

Transportation

China Railway First Group consortium wins bid for Gansu 1 billion railway dedicated line

04-03

Collect
Comment
Share

Retrieve password

Get verification code
Sure