Recently, the procurement of wind turbine equipment for the 800000 kilowatt wind power and 200000 kilowatt photovoltaic multi energy complementary project of the State Grid Energy Hami First Channel of Guoshen Company's Nanhu Power Plant was publicly tendered.
Project Overview
The 800000 kilowatt wind power and 200000 kilowatt photovoltaic multi energy complementary project site of State Grid Energy Hami First Channel is located in the Dananhu area of Hami, Xinjiang. The center of this project is approximately 96km away from Hami City in a straight line, forming an irregular polygon and covering an area of approximately 165.05km ², The elevation of the site is 885m~1009m, and the 091 County Road (to Yamansu Town) passes through the east side of the project site, providing convenient external transportation conditions. The wind farm of this project plans to install 128 6.25MW wind turbines, with a total installed capacity of 800MW. The wind farm is divided into two sections: Section A with a capacity of 400MW and Section B with a capacity of 400MW.
The project is scheduled to commence before September 30, 2023; Full capacity grid connected power generation before June 30, 2024.
Obtaining bidding documents
The start time for purchasing the bidding documents is 09:00:00 on August 25, 2023, and the deadline for purchasing the bidding documents is 16:00:00 on August 30, 2023. Editor/Zhao E
Comment
Write something~