HUADIAN CORPORATION Mangya Lenghu Wind Power Project Progress!
Seetao 2023-10-10 09:01
  • This project is the wind power project with the largest single unit capacity in inland high-altitude and cold areas
  • The total investment of the project is approximately 2.85 billion yuan. After completion, the annual power generation is expected to be 1.41 billion kilowatt hours.
Reading this article requires
8 Minute

The "chasing the wind" will not stop, and the "double festival" will not stop. On September 28, 2023, with the blades and hubs of the last 6.7-MW wind turbine set accurately docked in place, HUADIAN CORPORATION LTD. QINGHAI COMPANY Mangya Lenghu 500,000-kilowatt wind power project successfully completed the hoisting of all 75 wind turbines. Entering the stage of debugging and grid-connected power generation, the charge for the project to be put into production has been fully sounded.

This project is one of the first large-scale wind and solar base projects in the country. It is located in the no-man’s land of the Gobi Desert in Lenghu, Qinghai. The project is at an altitude of nearly 3,000 meters. It is designed to install a wind turbine unit with a single unit capacity of 6.7 MW. It is the largest single unit capacity in inland high-altitude and cold areas. Wind power projects. The total investment of the project is about 2.85 billion yuan. After completion, the annual power generation is expected to be 1.41 billion kilowatt-hours. It can save about 433,000 tons of standard coal every year and reduce sulfur dioxide emissions by 227.3 tons. The environmental and economic benefits are significant.

Command from the front and make overall arrangements

Faced with multiple difficulties such as tight project schedule, heavy tasks, and poor construction conditions, the project department consolidated responsibilities, clarified time, actively resolved problems and conflicts encountered during the construction process, and arranged dedicated personnel to keep an eye on the control process and equipment manufacturing progress to ensure that the wind turbine Equipment components and large mechanical equipment were successfully put in place, effectively ensuring the supply of equipment.

Overcome difficulties and forge ahead

The project department did not wait and took the initiative, giving full play to the spirit of "wind chasers". With the work style of "do it right away, get it done right", it carefully organized and scientifically planned to actively overcome the cold and windy sand, remote location, and complex terrain. and other unfavorable factors, all hoisting work was successfully completed with high intensity and efficiency, creating favorable conditions for the full-capacity grid connection of the project.

Party building leads the way, gathering energy and empowering

The temporary party branch of the project actively plays the vanguard and exemplary role of the party organization's battle fortress and party members in major engineering projects, organizes party members and cadres to show their identities, be pioneers, set up flags, overcome difficulties, strive to be the first, and cooperate with all participating units to make The project team had stronger cohesion and stronger combat effectiveness, and successfully completed the hoisting task of all 75 wind turbines in 132 days.

In the next step, the Mangya Lenghu Wind Power Project will take the opportunity of the special event of "striving to be the first and tackling difficulties in a hundred days" to sprint towards the annual production target, unify its thinking, work hard, and go all out to promote wind turbine debugging and collection line group tower wiring. We will wait for follow-up work to ensure that the full-capacity grid connection and commissioning tasks are completed by the end of the year. Editor/Xu Shengpeng


Comment

Related articles

Wind power

1.422 billion kilowatt hours! Gansu Qinghai Green Power Direct Connection Project Approved

04-03

Wind power

The heart of the world's largest offshore wind power flexible straight project sets sail!

04-03

Wind power

Fujian Ningde 300 MW offshore wind power project launched

04-01

Wind power

China and Kazakhstan jointly launch 1 gigawatt wind and solar energy storage project

04-01

Wind power

58 billion yuan! Gia Lai wind power complex project cooperation landing

03-31

Wind power

Future wind power development revolves around five core directions

03-31

Collect
Comment
Share

Retrieve password

Get verification code
Sure