In 2020, the urban road construction plan for the central city of Chongqing will involve a total of 97 projects, mainly the construction of 9 bridges, 8 tunnels and 920 kilometers of roads in the central city of the main city.

9 bridges and 8 tunnels will be built in the center of the main city
The 9 river-crossing bridges are: Baijusi Yangtze River Bridge, Zengjiayan Jialing River Bridge, Hongyan Village Jialing River Bridge, Water and Soil Jialing River Bridge, Caijia Jialing River Bridge, Guojiatuo Yangtze River Bridge, Lijia Jialing River Bridge, Huangjuituo Yangtze River Bridge, Ma'anshi Jialing River Bridge Double track bridge.
The 8 mountain tunnels are: Longxing Tunnel (Tongluo Mountain), Landlord Tunnel (Zhongliang Mountain), New Yanwei Mountain Tunnel (Tongluo Mountain), Tieshanping Double Track Tunnel (Tongluo Mountain), Jinfeng Tunnel (Jinyun Mountain) , University Town double-track tunnel (Zhongliang Mountain), Taojia Tunnel (Zhongliang Mountain), Lujiao Tunnel (Tongluo Mountain).

Actively explore the fast-track construction model
With regard to the construction of transportation infrastructure in the main urban area, the construction model of fast-track channels will be actively explored. The east-west trunk road of Xiema Tunnel and the main line of the west extension of Huayan Tunnel have been successfully completed and opened to traffic.
At the same time, speed up the construction of projects under construction such as the Jinfeng Tunnel and the first vertical line of the expressway to complete the operation as soon as possible; strive to start the Liangjiang New Area-Changshou Expressway by the end of 2020; accelerate the main city center to Yongchuan, Hechuan, Fuling, Qijiang Wansheng4 The preliminary research work for a fast-track channel is actively planning the main city center city-fulcrum city-bridgehead cities such as Rongchang and Tongnan.
In terms of the construction of secondary arterial roads and branch road networks, we will make every effort to promote the construction of 333 kilometers of secondary branch road networks, and accelerate the opening of 95 unconnected roads in the central urban area of the main city, with a total length of 73 kilometers.

25 new pedestrian bridges and underground passages
In 2020, the main urban area plans to start construction of 25 pedestrian bridges and underground passages, including 5 in Shapingba District, 3 in Banan District, 1 in Dadukou District, 2 in Jiangbei District, 3 in Nan'an District, and 3 in Beibei District. , 1 in Yuzhong District, 1 in Yubei District, 2 in Jiulongpo District, 1 in High-tech Zone, 3 in Liangjiang New District, and strive to complete 9 in 2020. Up to now, the No. 2 pedestrian bridge in Gao Vocational City, Banan District has been completed, another 16 are under construction, and 8 are in the preliminary work.
In addition, in 2020, there will be a total of 76 new projects and a total of about 30,800 parking spaces in the public parking lot construction plan in the central city of the main city in 2020. Among them: 15 new public parking lots will be constructed and about 4,300 new parking spaces will be added. Build 61 public parking lots and increase about 26,500 parking spaces.
In the future, these projects will help the interconnection of Chongqing's main city metropolitan area, promote the construction of a one-hour commuter circle, further improve the regional road network structure, and allow urban road construction to continue to expand into the main city metropolitan area. Editor/He Yuting