With a CPG500 track laying machine, rows of sleepers and two 400-meter-long steel rails are steadily dropped on the roadbed. It marks the successful trial laying of the second phase of the rail project of the Arab Railways, and the track laying base DMB's uplink CH43+720-CH44+920 becomes the first track laying on the whole line.

If you don't donate money, you will be successful. After the trial laying was successful, the owner immediately sent a congratulatory letter, expressing his conviction on the efficient trial laying technology, praising all the construction staff for their unremitting efforts against the scorching sun and the scorching heat, and would like to work together to promote the smooth realization of the track construction period;

The trial laying also received great attention from the branch and various projects. The branch leader An Haitao made a special trip to the site to praise the trial laying results and encourage the construction staff.

In order to ensure the smooth progress of track laying and strictly control the construction progress and quality, and promote the model approach and standard first, the test section of this section of track engineering is specially laid to provide a demonstration for the subsequent construction of other sections of the track, so as to fulfill the requirements of the overall construction period and achieve the smooth realization of the formal track laying. Create conditions.

The trial paving section adopts the "machine paving method", the mileage is DMB uplink CH 43+720-CH44+920, the total length is 1200 meters, the number of sleepers used is 2010, the number of 400m long rails is 3 pairs, and the long paving unit and other equipment are 36 Taiwan, 76 people participated in track laying.

The trial laying strictly and orderly carried out the seven major processes of rail material loading, rail laying unit and double-decker wagons, long rail entry, ground roller placement, rail docking, cloth sleeper rail collection, and installation of fasteners.

Before the trial shop, the preparation work was orderly and vigorously advanced. The project department prepares the construction plan for the construction site and line conditions in advance, and formulates a practical construction schedule;


At the same time, arrange on-site personnel to do equipment operation and maintenance training, continue to refine the division of responsibilities, and implement safety responsibilities; strictly control quality and safety training, strengthen coordination and communication between various departments and work areas, and implement "daily maintenance" of track laying equipment , Security personnel standing by and other systems; Arrange special personnel to carry out all-round and three-dimensional management of the on-site driving dispatch to ensure the success of the trial shop.

Go on a passionate mission, and the mission must be achieved. Now in the endless desert, a winding dragon is rising from the ground. In the next step, all the staff involved in the construction of the railway project department will use practical actions to fulfill their promises and strive to make the second phase of the railway construction a high-quality project. Editor/Wang Jiangwen