Nantong Port Yangkou to Lusi Port Railway Project Won the Bid
Seetao 2021-05-08 14:55
  • The railway connects with Haiyang Railway Beiyu Station in the north and Ningqi Railway in the south
Reading this article requires
8 Minute

On May 8, 2021, China Railway Shanghai Design Institute and China Railway Fourth Survey and Design Institute won two bid sections of the Nantong Port Yangkou Port Area to Lusi Port Area Railway Project, with a total investment of 5.94 billion yuan.

Railway project overview

Nantong Port Yangkou Port Area to Lusi Port Area Railway Link Project Yanglu Railway Project has a total length of about 85km and a total investment of about 9.9 billion yuan. The project passes through Qidong City, Haimen District, Demonstration Zone, and 4 counties and urban areas of Rudong County. 7 new stations (Dayu Station, Donghu Station, Tongzhou Bay Station, Zhengyu Station, Dongzao Port Station, Lusigang South Station, Lvsigang station, renovated two connection stations, Beiyu Station and Lvsi Station.

China Railway Shanghai Design Institute won the bid for the YLTLZCB1 tender. All the construction drawing designs within the scope of the project’s bidding mainly include the preliminary design corresponding to the pre-station engineering bridges, subgrades, track laying and beams, etc. All projects, related projects of Dongzao Port and Lusi Port South Passenger Transport, survey, construction drawing budget and list preparation, design follow-up services; procurement, engineering construction: including but not limited to the preliminary design content corresponding to the preliminary design budget of this project, relocation of road , Highway bridges, interchange drainage, cutting roots, changing rivers and ditches, sound insulation windows, temporary land use, roadbeds, bridges, tracks, passenger transport related projects, houses and accessories, water supply and drainage, vehicles, station construction, public works, sound barriers , Dalin Project, Fourth Power Project, Lusi Station Reconstruction Project, etc., joint commissioning and joint test, trial operation cooperation, etc., as well as the construction of temporary works necessary for the implementation of the above projects and the repair of defects during the warranty period, excluding requisition and demolition The three power and pipeline relocation projects.

China Railway Fourth Survey and Design Institute won the bid for the YLTLZCB2 tender. All the construction drawing designs within the scope of the project’s bidding (mainly including bridges in front of the station, roadbeds, track laying and beams, etc. All the projects corresponding to the preliminary design of the reform, Dayu and Donghu passenger transport functions), survey (survey), construction drawing budget and inventory preparation, design follow-up services; procurement, engineering construction: including but not limited to the corresponding preliminary design estimates of the project The preliminary design content of the project is to relocate roads, highway bridges, interchange drainage, cutting roots, changing rivers and ditches, sound insulation windows, temporary land, roadbeds, bridges, tracks, passenger transportation related projects, houses and accessories, water supply and drainage, vehicles, stations Site construction, public works, sound barriers, Dalin Project, Four Power Projects, Beiyu Station Reconstruction Project, etc., joint debugging and joint testing, trial operation cooperation, etc., as well as the construction of temporary works necessary for the implementation of the above projects and the repair of defects during the warranty period Etc., excluding the three power and pipeline relocation projects in the requisition and demolitionEditor/Xing Wentao、 Design/Wang Xia

Comment

Related articles

Transportation

Construction of Pingliang Section of Pingqing Railway officially started

04-25

Transportation

America's first real high-speed rail begins construction

04-24

Transportation

Construction of $211 million Philippine highway begins

04-23

Transportation

The first tunnel project of Jilin Bailin Expressway starts

04-22

Transportation

The railway is expected to open by the end of this year

04-22

Transportation

Construction of Lanxi Section of Jianwu Expressway is about to begin

04-19

Collect
Comment
Share

Retrieve password

Get verification code
Sure